Timeline

Fire Station No. 1 Construction

Date
Description
2019 
City Council signed the purchase agreement contingent on soil/land analysis
January 2020
Completion of soil/land analysis | Design and development
April 15, 2020
Design development ends
April 16, 2020
Construction Document Stage begins
April 27, 2020
Planning Commission meeting
May 5, 2020
City Council meeting | Design development approval
Aug. 4, 2020
City Council meeting | Construction document approval 8/4
Aug. 5, 2020
 Advertise for bid
Aug. 27, 2020
Public bid opening
Sept. 8, 2020
City Council approval of contracts
Sept. 20, 2020
Ground breaking ceremony
Fall 2021
Anticipated completion