The Burnsville Heights Area is planned for a 2018 street reconstruction project.  This street reconstruction project consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs.

Contacts
Project Manager: Assistant City Engineer John Schmeling
Project Inspector: Engineering Technician Cody Pietz

Links
Project Status Interactive Map
Burnsville Heights Area Project Phasing Map
Street Reconstruction Brochure
Public Hearing Notice
Burnsville Heights Area Neighborhood Meeting Invite
Burnsville Heights Area Map

Updates

July 12, 2018
Water service connections are complete in Phase 1.  The contractor is doing manhole reconstructions and storm sewer installation in Phase 1 Thursday 7/12/18 and Friday 7/13/18.  Grinding up of the remaining street in Phase 1 and the water main side of the street in Phase 2 is scheduled to start Monday 7/16/18.  Grading in Phase 1 is scheduled to begin on Tuesday 7/17/18 starting on Shirley Drive at Steven Road.  Water main installation in Phase 2 will start mid to late in the week of 7/16/18.  Please refer to the Project Status Interactive Map in the "Links" section of this page for more information.

July 6, 2018
Water main installation in Phase 1 is complete.  Temporary water main installation is underway in Phase 2.  Water service connections in Phase 1 have been rescheduled to start Monday 7/9/18 on Shirley Drive near Steven Road and progress around the Shirley Drive and Susan Lane loop.  Homes in phase 1 will be transferred over to the new water system after service connections are complete.  The contractor will drop off flyers and knock on doors to schedule service transfers.  Please refer to the Project Status Interactive Map in the "Links" section of this page for more information.

July 2, 2018
The Contractor is installing water main on Shirley Drive on the loop west of Susan Lane today (7/2/18) and tomorrow (7/3/18).  The Contractor is scheduled to start water service connections on Shirley Drive east of Steven Road starting Thursday (7/5/18).  The Contractor will not be working Wednesday 7/4/18.

June 27, 2018
The Contractor is installing water main in Phase 1 and is on Susan Lane working north from Shirley Drive.  The Contractor plans to complete water main installation on Susan Lane first then move to the Shirley Drive loop west of Susan Lane.  Main line water main installation in Phase 1 is expected to be completed around Thursday 7/5/18.  The Contractor will begin connecting homes in Phase 1 to the new water main after the main installation is complete.  Please refer to the Project Status Interactive Map in the "Links" section of this page for more information.

June 20, 2018
The Contractor is connecting homes in Phase 1 to the temporary water main the week of 6/18/18.  Water main replacement is scheduled to start on Monday 6/25/18.  Please refer to the Project Status Interactive Map in the "Links" section of this page for more details.

June 11, 2018
The Contractor will be constructing the project in two phases per the Burnsville Heights Area Project Phasing Map.  The Contractor is setting up temporary water main in phase 1 of the project.  The Contractor is scheduled to reclaim phase 1 streets on the water main side of the streets starting Tuesday, 6/12/18 at 7 am.  Access to properties will be maintained as feasible.  However, when the construction passes a driveway the access will be shut down during the day.  Access will be restored in the evening before the contractor leaves each day.  Please refer to the Project Status Interactive Map in the "Links" section and this web page for detailed updates.

May 17, 2018
The Contractor is tentatively scheduled to start street reclamation and temporary water main setup on or around Monday, 6/4/18.  Please refer to the Project Status Interactive Map and this web page for detailed updates.

April 18, 2018
The City Council awarded a construction contract to Northdale Construction Company, Inc. at their April 17, 2018 regular meeting.  The contractor is tentatively scheduled to start the project around middle to late May 2018.  An Open House is scheduled for Thursday, May 3, 2018 from 3:30 pm to 6:00 pm in the City Council Chambers at Burnsville City Hall, 100 Civic Center Parkway.  Residents in the project area will be sent an invitation to this meeting.  Engineering staff will be available to answer questions about construction, the contractor’s proposed schedule, and will take comments concerning the improvements.

March 12, 2018

A Public Hearing was held on March 6, 2018.  The City Council ordered the improvements, approved the plans & specifications and ordered advertisement for bids.  Bids will be received in early April and a contract will be awarded at the April 17, 2018 City Council meeting.

February 23, 2018

The City Council received the Preliminary Report for this project at their February 20, 2018 regular meeting.  A Public Hearing is scheduled for Tuesday, March 6, 2018, at 5:30 p.m. in the City Council Chambers at Burnsville City Hall, 100 Civic Center Parkway.  The Public Hearing is a meeting where the City Council receives public testimony regarding the improvement.  You are invited to address the City Council if you have concerns with any portion of the project.  Public Hearing notices and invitations have been mailed to effected property owners.  The Public Hearing Notice is available in the "Links" section of this page.

January 2, 2018

A neighborhood meeting is being held on Wednesday, January 17, 2018 from 3:30 to 6:00 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project.  Formal invitations have been mailed to effected property owners and a sample invite is available in the "Links" section of this page. 